MTA Construction Projects: Second Avenue Subway, IBX, New Trains & More
Every project in the MTA's capital project tracker: what it is, what it costs and when it should be done, updated monthly · Not affiliated with the MTA
The biggest projects
By estimated cost (or goal cost if there is no estimate yet). Finish is the MTA's current estimate.
| Project | Stage | Cost | Finish |
|---|---|---|---|
| Purchase 316 M9A Railcars This project purchases new 316 M9A railcars for the Long Island Rail Road and Metro-North Railroad, modernizing the fleet and improving reliability, customer comfort, and onboard systems. Metro-North Railroad | Construction | $2.9 billion | Dec 2028 |
| SAS Ph2: Heavy Civil TBM 116 St / 125 St Stns: Contract 2 As part of the overall Second Ave Subway Phase 2 project, this contract advances tunnel construction and related structural work near future 116 St and 125 St station areas. MTA Capital Construction Company | Construction | $2.1 billion | Sep 2029 |
| CBTC: Fulton/Liberty Lines As part of the MTA’s signal modernization program, we’re installing Communications-Based Train Control (CBTC) on the Fulton Street Line in Brooklyn and the Liberty Avenue Line in Queens, which serve… New York City Transit | Construction | $1.9 billion | May 2032 goal was Dec 2031 |
| Purchase 378 New B-Division Cars (R268) This project purchases new R268 subway cars for the B Division to modernize the fleet and improve reliability and the customer experience. New York City Transit | Construction | $1.6 billion | Jul 2030 |
| Purchase 435 B-Division Cars - R211 Option 2 This project purchases additional R211 subway cars for the B Division to modernize the fleet and improve reliability and the customer experience. New York City Transit | Construction | $1.4 billion | Nov 2028 |
| NYCT ADA Station Improvements: Package 5 As part of the MTA’s commitment to systemwide accessibility, we are making 13 stations accessible. This project will add new elevators or ADA accessible ramps to stations across New York… Staten Island Railway, New York City Transit | Construction | $854 million | Dec 2027 goal was Dec 2026 |
| NYCT ADA Station Improvements: Package 3 As part of the MTA’s commitment to systemwide accessibility, we are making accessibility improvements at 13 stations. This project includes eight stations being made newly accessible and five stations receiving… New York City Transit | Construction | $664 million | Dec 2026 goal was Jun 2026 |
| VNB Ph.2 -Reconstruction of Upper Level Approach This project will rehabilitate and reconstruct portions of the Verrazzano-Narrows Bridge upper-level approach ramps and reconfigure exits to improve safety and traffic flow. Bridges And Tunnels | Construction | $536 million | Jul 2029 |
| NYCT ADA: Package 2 We made six stations newly accessible—Westchester Sq–E Tremont Av, 181 St, Queensboro Plaza, 8 Av, Court Sq, and Woodhaven Blvd—and replaced elevators at Marcy Av and Flushing Av. The package… New York City Transit | Complete | $455 million | Dec 2024 goal was Jan 2024 |
| NYCT ADA Station Improvements: Package 6 As part of the MTA’s commitment to systemwide accessibility, we are making five stations accessible—Norwood Av (J/Z), Myrtle Av (J/M/Z), Avenue I (F), Burnside Av (4), and Middletown Rd (6)—and… New York City Transit | Construction | $437 million | Oct 2028 |
| Purchase 45 Locomotives This project purchases new diesel-battery hybrid locomotives that support maintenance and construction work across the subway system while reducing emissions in tunnel environments. New York City Transit | Construction | $416 million | Sep 2029 |
| NYCT ADA Station Improvements: Broadway Junction We are making crucial investments to improve accessibility, circulation, and design at Broadway Junction, Brooklyn's third largest subway station. We’re adding 7 new elevators, a new entrance on Van Sinderen… New York City Transit | Construction | $387 million | Sep 2027 |
Second Avenue Subway Phase 2
Contracts listed in the tracker so far. See mta.info for the whole project.
Phase 2 takes the Q train up Second Avenue from 96 St to 125 St in East Harlem, with new stations at 106 St, 116 St and 125 St.
| Contract | Stage | Cost | Finish |
|---|---|---|---|
| SAS Ph2: Heavy Civil TBM 116 St / 125 St Stns: Contract 2 MTA Capital Construction Company | Construction | $2.1 billion | Sep 2029 |
Interborough Express (IBX)
The MTA's own description from the tracker.
The Interborough Express is a transformative rapid transit project that will connect currently underserved areas of Brooklyn and Queens. It will substantially cut down on travel times between the two boroughs, reduce congestion, and expand economic opportunities for the people who live and work in the surrounding neighborhoods. The project would be built along the existing, LIRR-owned Bay Ridge Branch and CSX-owned Fremont Secondary, a 14-mile freight line that extends from Bay Ridge, Brooklyn, to Jackson Heights, Queens. It would…
Stage: Planning (Planned).
New trains, cars and buses
| Order | Stage | Cost | Finish |
|---|---|---|---|
| Purchase 316 M9A Railcars Metro-North Railroad | Construction | $2.9 billion | Dec 2028 |
| Purchase 378 New B-Division Cars (R268) New York City Transit | Construction | $1.6 billion | Jul 2030 |
| Purchase 435 B-Division Cars - R211 Option 2 New York City Transit | Construction | $1.4 billion | Nov 2028 |
| Purchase 45 Locomotives New York City Transit | Construction | $416 million | Sep 2029 |
| Purchase 131 Express Buses New York City Transit | Construction | $131 million | May 2026 |
| Purchase 21 Articulated Buses New York City Transit | Construction | $31 million | Feb 2028 |
Making stations accessible
22 accessibility projects (elevators, ramps and station rebuilds). The biggest 15 are shown.
| Project | Stage | Cost | Finish |
|---|---|---|---|
| NYCT ADA Station Improvements: Package 5 Staten Island Railway, New York City Transit | Construction | $854 million | Dec 2027 goal was Dec 2026 |
| NYCT ADA Station Improvements: Package 3 New York City Transit | Construction | $664 million | Dec 2026 goal was Jun 2026 |
| NYCT ADA: Package 2 New York City Transit | Complete | $455 million | Dec 2024 goal was Jan 2024 |
| NYCT ADA Station Improvements: Package 6 New York City Transit | Construction | $437 million | Oct 2028 |
| NYCT ADA Station Improvements: Broadway Junction New York City Transit | Construction | $387 million | Sep 2027 |
| LIRR ADA Station Improvements: Package 2 Long Island Rail Road | Construction | $328 million | Nov 2027 |
| NYCT ADA: Package 1 Staten Island Railway, New York City Transit | Complete | $325 million | Apr 2024 goal was Aug 2023 |
| NYCT ADA Station Improvements: Package 9 New York City Transit | Construction | $274 million | Dec 2028 |
| NYCT ADA Station Improvements: Package 4 New York City Transit | Construction | $222 million | Sep 2026 goal was Jun 2025 |
| NYCT ADA: Package 7 New York City Transit | Construction | $180 million | Aug 2028 |
| LIRR ADA Station Improvements: Package 1 Long Island Rail Road | Complete | $169 million | Dec 2025 goal was Sep 2025 |
| NYCT ADA Station Improvements: 149 St Complex & Tremont Av New York City Transit | Construction | $169 million | Jul 2026 goal was Jul 2023 |
| NYCT ADA Station Improvements and Renewal: Borough Hall New York City Transit | Construction | $165 million | Aug 2026 goal was Apr 2025 |
| MNR ADA Station Improvements: Woodlawn, Botanic Garden, Williams Bridge Metro-North Railroad | Construction | $160 million | May 2027 |
| NYCT ADA Station Improvements: 42 St - Bryant Park Complex New York City Transit | Construction | $134 million | Nov 2028 |
Running late
17 projects have an estimated finish later than their goal. The ones furthest behind are shown first.
| Project | Stage | Cost | Finish |
|---|---|---|---|
| NYCT ADA Station Improvements: 149 St Complex & Tremont Av New York City Transit | Construction | $169 million | Jul 2026 goal was Jul 2023 |
| NYCT ADA Station Improvements: Package 4 New York City Transit | Construction | $222 million | Sep 2026 goal was Jun 2025 |
| NYCT ADA Station Improvements and Renewal: Borough Hall New York City Transit | Construction | $165 million | Aug 2026 goal was Apr 2025 |
| NYCT ADA Station Improvements: Package 5 Staten Island Railway, New York City Transit | Construction | $854 million | Dec 2027 goal was Dec 2026 |
| NYCT ADA: Package 2 New York City Transit | Complete | $455 million | Dec 2024 goal was Jan 2024 |
| NYCT ADA: Package 1 Staten Island Railway, New York City Transit | Complete | $325 million | Apr 2024 goal was Aug 2023 |
| NYCT ADA Station Improvements: Package 3 New York City Transit | Construction | $664 million | Dec 2026 goal was Jun 2026 |
| CBTC: Fulton/Liberty Lines New York City Transit | Construction | $1.9 billion | May 2032 goal was Dec 2031 |
| Install Bike Racks/Hastings Sidewalk Repair Metro-North Railroad | Construction | $1,698,779 | Jul 2026 goal was Mar 2026 |
| 1 Elevated Street Stair: Beach 44 St / FAR (S4AB-M4AB)[SBMP] New York City Transit | Construction | $2,095,976 | Dec 2026 goal was Aug 2026 |
| LIRR ADA Station Improvements: Package 1 Long Island Rail Road | Complete | $169 million | Dec 2025 goal was Sep 2025 |
| Passenger ID CCTV: Beach 90 St / RKY [SBMP] New York City Transit | Construction | $1,178,100 | May 2026 goal was Mar 2026 |
| 1 Subway Street Stair: 169 St / QBL (S2) [SBMP] New York City Transit | Construction | $967,330 | Dec 2026 goal was Oct 2026 |
| Passenger ID CCTV: Canal St & Franklin St / BW7 [SBMP] New York City Transit | Construction | $1,634,654 | Jun 2026 goal was Apr 2026 |
| 1 Subway Interior Stair: 14 St / 8AV (P7) [SBMP] New York City Transit | Construction | $771,483 | Dec 2026 goal was Nov 2026 |
Spending by agency
Listed costs; a project shared by two agencies is split evenly.
- New York City Transit
97 projects$10.1 billion - Metro-North Railroad
19 projects$3 billion - MTA Capital Construction Company
2 projects$2.1 billion - Bridges And Tunnels
12 projects$1.4 billion - Staten Island Railway
3 projects$718 million - Long Island Rail Road
25 projects$551 million - Security / Disaster Recovery
1 projects$0
Every project
Tap a stage to open the list.
Construction (66)
| Project | Stage | Cost | Finish |
|---|---|---|---|
| Purchase 316 M9A Railcars This project purchases new 316 M9A railcars for the Long Island Rail Road and Metro-North Railroad, modernizing the fleet and improving reliability, customer comfort, and onboard systems. Metro-North Railroad | Construction | $2.9 billion | Dec 2028 |
| SAS Ph2: Heavy Civil TBM 116 St / 125 St Stns: Contract 2 As part of the overall Second Ave Subway Phase 2 project, this contract advances tunnel construction and related structural work near future 116 St and 125 St station areas. MTA Capital Construction Company | Construction | $2.1 billion | Sep 2029 |
| CBTC: Fulton/Liberty Lines As part of the MTA’s signal modernization program, we’re installing Communications-Based Train Control (CBTC) on the Fulton Street Line in Brooklyn and the Liberty Avenue Line in Queens, which serve… New York City Transit | Construction | $1.9 billion | May 2032 goal was Dec 2031 |
| Purchase 378 New B-Division Cars (R268) This project purchases new R268 subway cars for the B Division to modernize the fleet and improve reliability and the customer experience. New York City Transit | Construction | $1.6 billion | Jul 2030 |
| Purchase 435 B-Division Cars - R211 Option 2 This project purchases additional R211 subway cars for the B Division to modernize the fleet and improve reliability and the customer experience. New York City Transit | Construction | $1.4 billion | Nov 2028 |
| NYCT ADA Station Improvements: Package 5 As part of the MTA’s commitment to systemwide accessibility, we are making 13 stations accessible. This project will add new elevators or ADA accessible ramps to stations across New York… Staten Island Railway, New York City Transit | Construction | $854 million | Dec 2027 goal was Dec 2026 |
| NYCT ADA Station Improvements: Package 3 As part of the MTA’s commitment to systemwide accessibility, we are making accessibility improvements at 13 stations. This project includes eight stations being made newly accessible and five stations receiving… New York City Transit | Construction | $664 million | Dec 2026 goal was Jun 2026 |
| VNB Ph.2 -Reconstruction of Upper Level Approach This project will rehabilitate and reconstruct portions of the Verrazzano-Narrows Bridge upper-level approach ramps and reconfigure exits to improve safety and traffic flow. Bridges And Tunnels | Construction | $536 million | Jul 2029 |
| NYCT ADA Station Improvements: Package 6 As part of the MTA’s commitment to systemwide accessibility, we are making five stations accessible—Norwood Av (J/Z), Myrtle Av (J/M/Z), Avenue I (F), Burnside Av (4), and Middletown Rd (6)—and… New York City Transit | Construction | $437 million | Oct 2028 |
| Purchase 45 Locomotives This project purchases new diesel-battery hybrid locomotives that support maintenance and construction work across the subway system while reducing emissions in tunnel environments. New York City Transit | Construction | $416 million | Sep 2029 |
| NYCT ADA Station Improvements: Broadway Junction We are making crucial investments to improve accessibility, circulation, and design at Broadway Junction, Brooklyn's third largest subway station. We’re adding 7 new elevators, a new entrance on Van Sinderen… New York City Transit | Construction | $387 million | Sep 2027 |
| LIRR ADA Station Improvements: Package 2 As part of the MTA’s commitment to systemwide accessibility, we are making improvements at the Forest Hills, Hollis, and Babylon LIRR stations. In addition to making these stations fully accessible,… Long Island Rail Road | Construction | $328 million | Nov 2027 |
| VNB Main Cable Dehumidification System -Ph1 This project installs a dehumidification system for the Verrazzano-Narrows Bridge main cables to reduce corrosion and extend the life of these critical structural elements. Bridges And Tunnels | Construction | $321 million | Aug 2029 |
| Installation of Fire Suppression System at Hugh L. Carey & Queens Midtown Tunnels We’re adding modern fire-suppression systems to the Hugh L. Carey and Queens Midtown Tunnels to improve safety. These upgrades systems will reduce smoke and heat in case of a fire… Bridges And Tunnels | Construction | $276 million | Nov 2028 |
| NYCT ADA Station Improvements: Package 9 As part of the MTA’s commitment to systemwide accessibility, we are making the Parsons Blvd F, Briarwood E/F, and Gates Av J/Z subway stations accessible and improving the station environment.… New York City Transit | Construction | $274 million | Dec 2028 |
| TNB Facility Painting This project delivers facility-wide painting and targeted structural rehabilitation at the Throgs Neck Bridge to protect steel and extend service life. Bridges And Tunnels | Construction | $243 million | Oct 2028 |
| NYCT ADA Station Improvements: Package 4 As part of the MTA’s commitment to systemwide accessibility, we are making the Bay Ridge-95 St R, 137 St City College 1, Northern Blvd MR, and Parkchester 6 subway stations… New York City Transit | Construction | $222 million | Sep 2026 goal was Jun 2025 |
| NYCT ADA: Package 7 As part of the MTA’s commitment to systemwide accessibility, we are making the 167 St B/D and Kingsbridge Rd 4 stations accessible. This project will add new elevators, relocate staircases,… New York City Transit | Construction | $180 million | Aug 2028 |
| Station Renewals: 3 Locations (6AV, PEL, QBL) This project delivers station improvements at the 7th Ave BQ, E 149th St 6, and 179th St F stations, including component repairs, water leak mitigation, and other improvements to the… New York City Transit | Construction | $172 million | Jan 2028 |
| NYCT ADA Station Improvements: 149 St Complex & Tremont Av As part of the MTA’s commitment to systemwide accessibility, we are making the 149 St Grand Concourse complex and Tremont Av BD stations accessible and improving the station environments. At… New York City Transit | Construction | $169 million | Jul 2026 goal was Jul 2023 |
| NYCT ADA Station Improvements and Renewal: Borough Hall As part of the MTA’s commitment to systemwide accessibility, we are making this station accessible and improving the station environment. This project will fully renew the Borough Hall 4/5 station… New York City Transit | Construction | $165 million | Aug 2026 goal was Apr 2025 |
| MNR ADA Station Improvements: Woodlawn, Botanic Garden, Williams Bridge As part of the MTA’s commitment to systemwide accessibility, we are making the Botanical Gardens, Williams Bridge, and Woodlawn Metro-North stations accessible and improving the station environment. We will completely… Metro-North Railroad | Construction | $160 million | May 2027 |
| NYCT ADA Station Improvements: 42 St - Bryant Park Complex As part of the MTA’s commitment to systemwide accessibility, we are making the Bryant Park-5 Av subway station complex accessible and improving the station environment. This project will make both… New York City Transit | Construction | $134 million | Nov 2028 |
| Purchase 131 Express Buses This project purchases new express buses for New York City Transit to modernize the fleet and support reliable service. New York City Transit | Construction | $131 million | May 2026 |
| Car Washer Component Repairs Keeping car washers in good condition supports fleet availability and cleanliness. This project repairs components of an existing car washer. New York City Transit | Construction | $110 million | May 2028 |
| Depot Boilers, HVAC & Misc: Kingsbridge, Flatbush,Charleston We’re upgrading three NYC Transit bus depots—Kingsbridge, Flatbush, and Charleston—to improve safety and reliability. New York City Transit | Construction | $99 million | Nov 2027 |
| Equip B Division with Second CBTC Radio: Hitachi Modern communications are essential for advanced train control. This project expands onboard CBTC radio capability on B Division fleets to support signal modernization and more reliable service. New York City Transit | Construction | $85 million | Mar 2028 |
| Elevated Structure Repairs: 9th Av Port to Stillwell Av/ WST This project performs structural repairs and painting from the 9th Ave portal to Stillwell Ave on the West End Line. This will provide protective coating that prevents corrosion and extends… New York City Transit | Construction | $65 million | Jan 2028 |
| Rehabilitation of 5 CBHs - Various Locations Power distribution equipment supports safe, reliable train service. This project rehabilitates circuit breaker houses at multiple locations to replace aging equipment and improve system reliability. New York City Transit | Construction | $56 million | Dec 2027 |
| Structural Repairs: 9 Ave / WST Line structures—bridges, viaducts, and tunnels—need sustained investment to slow deterioration. This project performs structural repairs at the 9 Ave (D) on the West End Line. New York City Transit | Construction | $45 million | Aug 2027 |
| Equip B Div w/ 2nd CBTC Radio This project advances the expansion of CBTC radio capability on B Division fleets, supporting signal modernization. New York City Transit | Construction | $45 million | Apr 2027 |
| Component Repairs: Coney Island Overhaul Facility Shops and yards keep fleets service-ready. This project delivers component repairs at the Coney Island Overhaul Facility. New York City Transit | Construction | $41 million | Apr 2028 goal was Mar 2028 |
| Rehabilitation of Manhattan Tunnel Entrance/Exit - Hugh L Carey Tunnel We’re improving the Manhattan entrance to the Hugh L. Carey Tunnel to make it safer and move traffic more smoothly. We’ll reconfigure the plaza, repave and restripe, upgrade lighting and… Bridges And Tunnels | Construction | $39 million | Aug 2026 |
| Widening of S/B FDR Drive - 125 St to 116 St This project adjusts the southbound FDR Drive between 125 St and 116 St to improve traffic flow and safety near the RFK Bridge approaches. The work includes replacing the East… Bridges And Tunnels | Construction | $34 million | Aug 2026 |
| Purchase 21 Articulated Buses This project purchases 21 articulated buses for New York City Transit to replace buses that have reached the end of their useful life and support more reliable service on high-ridership… New York City Transit | Construction | $31 million | Feb 2028 |
| DOS Facility Heating and Energy Efficiency Boiler Upgrades This project upgrades boilers and related systems at Department of Subways facilities to improve heating reliability and energy efficiency. New York City Transit | Construction | $30 million | Mar 2027 |
| South Shore Bridge Painting This project rehabilitates and repaints multiple LIRR bridges to protect structural steel from corrosion and extend service life. Long Island Rail Road | Construction | $17 million | May 2027 |
| Upgrade / Replace PBX-2 at Jay St We’re upgrading the station voice communications at the Jay Street complex. The new IP-based system will support Help Point intercoms, emergency and maintenance phones, booth lines, and station paging/announcements, with… New York City Transit | Construction | $15 million | Dec 2027 |
| VHF: Portable Radio Replacement Reliable radio communications support safe operations and emergency response. This project replaces portable Very-High Frequency (VHF) radios used by field staff to improve coverage and reliability. New York City Transit | Construction | $12 million | – |
| East New York Depot Fire Suppression System Rehabilitation This project rehabilitates and replaces aging fire suppression distribution piping at the East New York Bus Depot to improve overall reliability and performance of the system. New York City Transit | Construction | $10 million | Sep 2026 |
| Yard Lighting & Amenities This project replaces the lighting at Hillside Support Facility with more modern, energy efficient LED systems. Long Island Rail Road | Construction | $9,350,000 | Dec 2026 |
| Medford Ave and North Country Rd Bridge Painting This project rehabilitates and repaints select LIRR bridges, including structures over Medford Ave and North Country Rd, to provide protective coatings that slow corrosion and extend service life. Long Island Rail Road | Construction | $5,411,214 | Dec 2026 |
| Island Park Paving - SBMP This project rehabilitates pavement, drainage, pedestrian paths, and ADA features at Island Park, making access safer and more comfortable for customers. Delivered through the MTA's Small Business Mentoring Program (SBMP),… Long Island Rail Road | Construction | $5,110,000 | Mar 2027 goal was Feb 2027 |
| Morris Park Yard Drainage Improvements This project improves drainage and surfaces at the LIRR Morris Park Yard entrance and storage areas to improve site conditions, circulation, and stormwater performance. Long Island Rail Road | Construction | $4,966,835 | Dec 2026 |
| Atlantic Terminal Ticket Office HVAC This project replaces and upgrades HVAC systems serving the LIRR Atlantic Terminal ticket office and adjacent customer and staff areas to improve comfort and reliability. Long Island Rail Road | Construction | $4,964,660 | Aug 2026 |
| HVAC/Sanitary Sewer Connections This project replaces HVAC equipment at the Hicksville and Ronkonkoma stations and improves sewer connections at Ronkonkoma to support station operations and customer comfort. Long Island Rail Road | Construction | $3,988,988 | Oct 2026 |
| Main St & North Sea Rd Bridge Painting This project rehabilitates and repaints select LIRR bridges over Main St and North Sea Rd to provide protective coatings that slow corrosion and extend service life. Long Island Rail Road | Construction | $3,428,925 | Dec 2026 |
| W255th St Reconstruction @ Riverdale This project improves pedestrian access and circulation near the Metro-North Riverdale Station. Metro-North Railroad | Construction | $3,315,924 | Sep 2026 |
| 2 Subway Street Stairs: 179 St / QBL (S2/M2AB, S4/M4) [SBMP] This project repairs or replaces two subway street stairs at 179 St on the Queens Blvd Line to improve safety and station access. Delivered through the MTA's Small Business Mentoring… New York City Transit | Construction | $3,296,873 | Dec 2026 |
| 2 Sub Street Stairs: 169 St / QBL (S1/M1AB, S3/M3AB) [SBMP] This project repairs or replaces two subway street stairs at 169 St on the Queens Blvd Line to improve safety and station access. Delivered through the MTA's Small Business Mentoring… New York City Transit | Construction | $2,257,843 | Nov 2026 |
| 1 Subway Street Stair: 207 St / 8AV (S4/M5 A/B) [SBMP] This project repairs or replaces one subway street stair at 207 St on the 8 Av Line to improve safety and station access. Delivered through the MTA's Small Business Mentoring… New York City Transit | Construction | $2,182,600 | Oct 2026 |
| 1 Elevated Street Stair: Beach 44 St / FAR (S4AB-M4AB)[SBMP] This project repairs or replaces one elevated street stair at Beach 44 St on the Far Rockaway Line to improve safety and station access. Delivered through the MTA's Small Business… New York City Transit | Construction | $2,095,976 | Dec 2026 goal was Aug 2026 |
| Passenger ID CCTV: Christopher St & Houston St / BW7 [SBMP] This project upgrades communications and security systems at Christopher St and Houston St stations. Delivered through the MTA's Small Business Mentoring Program (SBMP), which helps small firms build capacity to… New York City Transit | Construction | $1,876,518 | Apr 2026 |
| Install Bike Racks/Hastings Sidewalk Repair This project installs new bike racks to support first/last-mile access for the community, repairs a portion of the pedestrian sidewalk, and improves the access path at Hastings-on-Hudson to better accommodate… Metro-North Railroad | Construction | $1,698,779 | Jul 2026 goal was Mar 2026 |
| Passenger ID CCTV: Canal St & Franklin St / BW7 [SBMP] This project upgrades communications and security systems at the Canal St and Franklin St stations to support safety and incident response. Delivered through the MTA's Small Business Mentoring Program (SBMP),… New York City Transit | Construction | $1,634,654 | Jun 2026 goal was Apr 2026 |
| Fleetwood Circulation Improvements This project improves circulation, adds ADA-comppliant markings, and rehabilitates parking areas at the Fleetwood station to make it easier for all riders to access the station. Metro-North Railroad | Construction | $1,611,718 | Apr 2026 |
| 3 Subway Interior Stairs: Elmhurst Av / QBL (P3,P4,P5)[SBMP] This project repairs or replaces three interior stairs at Elmhurst Av on the Queens Blvd Line to improve circulation and station safety. Delivered through the MTA's Small Business Mentoring Program… New York City Transit | Construction | $1,342,314 | Nov 2026 |
| 1 Subway Street Stair: Jamaica Center / ARC (S1/M1/M3)[SBMP] This project repairs or replaces one subway street stair at Jamaica Center on the Archer Av Line to improve safety and station access. Delivered through the MTA's Small Business Mentoring… New York City Transit | Construction | $1,264,235 | Oct 2026 |
| Passenger ID CCTV: Beach 90 St / RKY [SBMP] This project upgrades communications and security systems at Beach 90 St on the Rockaway Line to support safety and incident response. Delivered through the MTA's Small Business Mentoring Program (SBMP),… New York City Transit | Construction | $1,178,100 | May 2026 goal was Mar 2026 |
| 1 Subway Street Stair: 169 St / QBL (S2) [SBMP] Station stairs need periodic replacement to stay safe and functional. This project repairs or replaces one subway street stair at 169 St on the Queens Blvd Line. Delivered through the… New York City Transit | Construction | $967,330 | Dec 2026 goal was Oct 2026 |
| 1 Subway Street Stair: Queens Plz / QBL (S5/M5A/B/C) [SBMP] This project repairs or replaces a stair. Delivered through the MTA's Small Business Mentoring Program (SBMP), which helps small firms build capacity to deliver MTA work. New York City Transit | Construction | $918,520 | Dec 2026 |
| 1 Subway Street Stair: 179 St / QBL (S15/M15) [SBMP] This project repairs or replaces one subway street stair at 179 St on the Queens Blvd Line to improve safety and station access. Delivered through the MTA's Small Business Mentoring… New York City Transit | Construction | $897,119 | Oct 2026 |
| 1 Sub Street Stair: Vernon-Jackson / FLS (S2/M5/M2AB)[SBMP] This project repairs one subway street stair at Vernon Blvd-Jackson Av on the Flushing Line to improve safety and station access. Delivered through the MTA's Small Business Mentoring Program (SBMP),… New York City Transit | Construction | $802,525 | Apr 2026 |
| 1 Subway Street Stair: Grand AV/QBL (S2) [SBMP] This project repairs or replaces one subway street stair at Grand Av on the Queens Blvd Line to improve safety and station access. Delivered through the MTA's Small Business Mentoring… New York City Transit | Construction | $778,250 | May 2026 |
| 1 Subway Interior Stair: 14 St / 8AV (P7) [SBMP] This project repairs or replaces a stair. Delivered through the MTA's Small Business Mentoring Program (SBMP), which helps small firms build capacity to deliver MTA work. New York City Transit | Construction | $771,483 | Dec 2026 goal was Nov 2026 |
| 1 Subway Str Stair: 8 St / BWY (S5) [SBMP] This project repairs or replaces one subway street stair at 8 St on the Broadway Line to improve safety and station access. Delivered through the MTA's Small Business Mentoring Program… New York City Transit | Construction | $696,320 | Apr 2026 |
Procurement (65)
| Project | Stage | Cost | Finish |
|---|---|---|---|
| SIR Stations and Structures Program (2020-24) This program invests in the structural rehabilitation at the Garretson Ave Bridge and Stapleton Viaduct along with station component repairs at Staten Island Railway stations. Staten Island Railway | Upcoming Procurement | $128 million | Jun 2029 |
| Rehab: Police District Office #4 - 14 Street-Union Square Station and support facilities need periodic renewal to stay safe and functional. This project rehabilitates the Police District Office at 14 St–Union Square. New York City Transit | Upcoming Procurement | $48 million | Feb 2028 |
| Hunter North and South Substations MTA substations convert utility power into the 650-volt DC that moves trains. This project reinvests in the Hunter North and South substations on the E & M lines to replace… New York City Transit | Upcoming Procurement | – | – |
| Grand Central Terminal Security Cameras & Expansion Communications and security systems support safe operations and incident response. This project upgrades and expands security camera coverage at Grand Central Terminal. Metro-North Railroad | Upcoming Procurement | – | – |
| Station Renewal: Chambers St / Nassau Line This project renews Chambers St on the Nassau St Line with targeted repairs and upgrades to improve the station environment. New York City Transit | Upcoming Procurement | – | – |
| Rehabilitate Emergency Exits: Various Locations System-wide This project rehabilitates emergency exits at select locations and upgrades life-safety features to improve emergency evacuation conditions. New York City Transit | Upcoming Procurement | – | – |
| Elevator Replacement at the Kingsbridge and Michael J. Quill Bus Depots This project replaces four elevators at two at Kingsbridge and two at the Michael J. Quill Depot with modern units. New York City Transit | Upcoming Procurement | – | – |
| Rehab Ducts: Hanover Sq/Pearl St Substation - CLK This project rehabilitates substation ducts serving the Hanover Sq / Pearl St substation to support reliable traction power. New York City Transit | Upcoming Procurement | – | – |
| Station Work: 4 Locations/Second Avenue This project will upgrade selected station components to address current operating experience. This work will be delivered at four locations on the Second Avenue (Q) line. New York City Transit | Upcoming Procurement | – | – |
| Sandy Resiliency (Street Level Openings): Various Locations System-wide As part of the MTA's resilience program, this project evaluates and advances protections for select street-level openings and other vulnerabilities to reduce flood and coastal surge risk in the subway… Security / Disaster Recovery | Upcoming Procurement | – | – |
| Public Address / Customer Information Screens: Upgrade Legacy Systems at 71 B-Division Stations Customer information systems help riders navigate the system. This project upgrades legacy public address and customer information systems at B Division stations, improving announcements and digital signage for clearer service… New York City Transit | Upcoming Procurement | – | – |
| Signal Uninterrupted Power Supply System Upgrade This project upgrades Uninterruptible power supplies (UPS) equipment to improve reliability for essential communications and controls during outages. New York City Transit | Upcoming Procurement | – | – |
| CBTC: Queens Boulevard East Install Signals and train control enable safe, reliable train movements. This project installs CBTC on Queens Boulevard East to modernize the signal system. New York City Transit | Upcoming Procurement | – | – |
| CBTC 6 Av / 63 St (Signal System and Selected Adjacent Infrastructure) Signals and train control enable safe, reliable train movements. This project installs Communications-Based Train Control (CBTC) on the 6 Av/63 St corridor to modernize the signal system and improve service… New York City Transit | Upcoming Procurement | – | – |
| DCE Shop Components: Various Facilities (2020-2024) Maintenance facilities require regular replacement of worn systems. This project replaces shop components across various facilities. Exact locations to be announced on Solicitation Notice. New York City Transit | Upcoming Procurement | – | – |
| Bridge Replacement Program - Highway Bridges Bridges must be renewed to maintain safety and extend service life. This program replaces aging highway bridges. Exact locations to be announced on Solicitation Notice. Long Island Rail Road | Upcoming Procurement | – | – |
| Structural Repairs and Painting, 9th Ave Portal to Stillwell Elevated structures need steel repair and protective coatings to prevent corrosion. This project performs structural repairs and painting from the 9th Ave portal to Stillwell Ave on the (D) line. New York City Transit | Upcoming Procurement | – | – |
| Rebuild Marble Hill Retaining Wall - Phase 1 This project advances inspection, design, and priority repairs for the Marble Hill retaining wall along the Hudson Line to protect track stability and the right-of-way. Metro-North Railroad | Upcoming Procurement | – | – |
| Grand Central Terminal Fire Stand Pipe - Phase 2 This project continues replacement of the fire standpipe system in Grand Central Terminal to improve reliability. Metro-North Railroad | Upcoming Procurement | – | – |
| Moodna/Woodbury Viaduct Repairs Metro-North structures need targeted renewal to remain safe and reliable. This project repairs the Moodna and Woodbury viaducts. Metro-North Railroad | Upcoming Procurement | – | – |
| Train Wash Replacement Railcar washers are critical to fleet cleanliness and maintenance throughput. This project replaces an existing train wash facility. Long Island Rail Road | Upcoming Procurement | – | – |
| Electronic Security System: 1 Station Complex, Manhattan This project upgrades electronic security systems at a station complex in Manhattan to support safer operations and improved incident response. New York City Transit | Upcoming Procurement | – | – |
| ADA / Station Renewals: Brook Av & 3 Av-138 St / PEL As part of the MTA’s commitment to systemwide accessibility, we are making 3 Av–138 St and Brook Av (6) accessible and renewing both stations with new ADA boarding areas, upgraded… New York City Transit | Active Procurement | – | – |
| Fan Plant Component Repairs Ventilation plants support smoke control and emergency operations. This project repairs components at one or more fan plants. Exact locations to be announced on Solicitation Notice. New York City Transit | Upcoming Procurement | – | – |
| HVAC Upgrade at Herald Sq Track Employee Facility Employee facilities require reliable climate control for safe, continuous operations. This project upgrades HVAC at the Herald Sq track employee facility. New York City Transit | Upcoming Procurement | – | – |
| Structural Painting and Repair: Queensboro Plaza - 33 St / Flushing Line This project performs structural repairs and painting on the Flushing Line between Queensboro Plaza and 33 St. New York City Transit | Upcoming Procurement | – | – |
| Laser Intrusion Detection System (LIDS) Perimeter detection and security systems protect subway tracks from unauthorized intrusion. This project installs or upgrades a Laser Intrusion Detection System at stations throughout the system. New York City Transit | Upcoming Procurement | – | – |
| Track Intrusion Detection Prototype This project includes installation of track intrusion detection systems at select subway stations to help identify unauthorized access to the right-of-way and support safer operations. New York City Transit | Upcoming Procurement | – | – |
| Design-Build Services for ADA Upgrades Package 8 As part of the MTA’s commitment to systemwide accessibility, we are making five stations accessible - 18 Av (D), Fort Hamilton Pkwy (D), Jefferson St (L), Neptune Av (F), and… New York City Transit | Active Procurement | – | – |
| Design-Build Services for ADA Upgrades - Package 10 As part of the MTA’s commitment to systemwide accessibility, we are making three stations accessible - 2 Av (F), 7 Av (B,D,E), and Morrison Av-Soundview (6). New York City Transit | Active Procurement | – | – |
| 215 St Signal Shop Component Replacement Signal shops support systemwide signal reliability. This project replaces components at the 215 St signal shop. New York City Transit | Upcoming Procurement | – | – |
| Facade Repair: 4 Av Station / 6 Av Line This project rehabilitates facade elements at 4 Av Station on the 6 Av Line in Brooklyn. New York City Transit | Upcoming Procurement | – | – |
| Michael J. Quill Bus Depot: Expansion Joint, Beam, and Slab Repairs This project repairs structural components at the Michael J. Quill Bus Depot. New York City Transit | Upcoming Procurement | – | – |
| CBTC Canarsie Upgrade This project provides upgrades to the Canarsie Line CBTC system that will further improve reliability and support more consistent service. New York City Transit | Upcoming Procurement | – | – |
| Brooklyn Bridge - City Hall / LEX (Vents and Mezz Ceiling) This project addresses station vents and mezzanine ceiling work at Brooklyn Bridge–City Hall on the Lexington Ave line. New York City Transit | Upcoming Procurement | – | – |
| Hudson Line Slope Stabilization The stabilization project is focused on the Hudson Line in Yonkers. The project includes drainage and culvert improvements, slope stabilization, and retaining wall rehabilitation. This project is part of the… Metro-North Railroad | Upcoming Procurement | – | – |
| Structural Testing Systemwide This project performs targeted structural testing at select elevated structures to help prioritize repairs and improve safety. New York City Transit | Upcoming Procurement | – | – |
| Rehabilitation of Emergency Exits: 21 Locations Emergency egress infrastructure must be maintained systemwide. This project rehabilitates emergency exits at 21 locations. New York City Transit | Upcoming Procurement | – | – |
| Design-Build Services for ADA Upgrades Package 11 As part of the MTA’s commitment to systemwide accessibility, we are making three stations accessible - 110 St (6), 145 St (A,B,C,D), and Wakefield-241 St (2). New York City Transit | Active Procurement | – | – |
| Station State of Good Repair Work - Package 2 (27 Stations / Various Lines) This package delivers comprehensive station state-of-good-repair work to renew deteriorated components and improve safety, reliability, and the station environment. New York City Transit | Upcoming Procurement | – | – |
| Column Repairs: Rockaway, New Lots, and Liberty Line structures—bridges, viaducts, and tunnels—need sustained investment to slow deterioration. This project performs structural repairs and protections for column bases across multiple elevated lines. New York City Transit | Active Procurement | – | – |
| Station State of Good Repair Work - Package 3 (10 Stations / West End Line) This package delivers comprehensive station state-of-good-repair work to renew deteriorated components and improve safety, reliability, and the station environment. New York City Transit | Upcoming Procurement | – | – |
| Water Condition Remedy (2027-2028) This project addresses water conditions at select locations to improve reliability and protect critical assets. New York City Transit | Upcoming Procurement | – | – |
| Miscellaneous Structural Rehabilitation at the Verrazzano-Narrows Bridge This project delivers targeted structural rehabilitation work at the Verrazzano-Narrows Bridge to address deterioration and extend asset life. Bridges And Tunnels | Upcoming Procurement | – | – |
| Sign Gantry Upgrade at the Henry Hudson Bridge This project upgrades or replaces sign gantries at the Henry Hudson Bridge to improve safety and reliability for motorists. Bridges And Tunnels | Upcoming Procurement | – | – |
| Rehabilitation of the Governor's Island Vent Building and Brooklyn Vent Building Facade This project rehabilitates facade elements at the Governor's Island Vent Building and Brooklyn Vent Building to improve safety, waterproofing, and long-term condition. Bridges And Tunnels | Upcoming Procurement | – | – |
| Replacement of 13KV Substation at the Robert F. Kennedy Bridge This project replaces or relocates a 13 kV substation at the Robert F. Kennedy Bridge to modernize power infrastructure and improve reliability. Bridges And Tunnels | Upcoming Procurement | – | – |
| Laser Intrusion Detection System (LIDS) This project includes installation of perimeter detection systems to help protect tracks from unauthorized access. New York City Transit | Upcoming Procurement | – | – |
| Column and Overhead Steel Repair: 125 St Arch and 215 St- 225 St / Broadway 7 Av Line This project repairs columns and overhead steel in targeted segments on the Broadway-7 Av Line to improve structural condition and long-term reliability. New York City Transit | Upcoming Procurement | – | – |
| Reynolds Channel Viaduct and Wreck Lead Bridge Rehabilitation This project rehabilitates movable bridge infrastructure, upgrading control systems and mechanical equipment, improving power redundancy, repainting steel, and repairing concrete to improve reliability and extend service life. Long Island Rail Road | Upcoming Procurement | – | – |
| Fresh Pond Yard Bridge Replacement and Yard/Main Track Reconfiguration This project advances improvements to the Fresh Pond Yard to support safe, reliable operations. Long Island Rail Road | Upcoming Procurement | – | – |
| Station State of Good Repair Work - Package 6 (18 Stations / Various Lines) This package delivers station state-of-good-repair work to renew deteriorated components and improve safety, reliability, and the station environment. New York City Transit | Upcoming Procurement | – | – |
| Station State of Good Repair Work - Package 7 (9 Stations / Various Lines) This package delivers station state-of-good-repair work to renew deteriorated components and improve safety, reliability, and the station environment. New York City Transit | Upcoming Procurement | – | – |
| Electronic Security System: 1 Station Complex, Brooklyn This project upgrades electronic security systems at a station complex in Brooklyn to support safer operations and improved incident response. New York City Transit | Upcoming Procurement | – | – |
| Design Build Services for Westbound Bypass Part 2 This project will build new grade-separated railroad track to help remove conflicts and improve train movements into the East River Tunnel. Long Island Rail Road | Active Procurement | – | – |
| ADA Station Improvements - Package 3 As part of the MTA’s commitment to systemwide accessibility, we are making LIRR Bellerose and Floral Park stations accessible and making significant station improvements. Long Island Rail Road | Active Procurement | – | – |
| West Hempstead and Winfield Substation Replacements This project replaces substations at West Hempstead and Winfield to modernize aging infrastructure and improve power reliability. Long Island Rail Road | Upcoming Procurement | – | – |
| Rehabilitation of 5 Harlem Line Stations This project rehabilitates Hartsdale, Scarsdale, Crestwood, Chappaqua, and Pleasantville Metro-North Harlem Line stations through platform and canopy work, circulation and accessibility improvements, and upgrades to customer information and safety systems. Metro-North Railroad | Upcoming Procurement | – | – |
| Bridge Painting (Seaford Oyster Bay & Wantagh Parkway) This project advances design for painting and protective coating work on select LIRR bridges over the Seaford-Oyster Bay Expressway and the Wantagh State Parkway to protect steel and extend service… Long Island Rail Road | Upcoming Procurement | – | – |
| Security Towers at the Marine Parkway Bridge and Cross Bay Bridge This project installs or upgrades security towers at the Marine Parkway Bridge and Cross Bay Bridge to support monitoring and incident response. Bridges And Tunnels | Upcoming Procurement | – | – |
| Sign Gantry Upgrades at the Marine Parkway Bridge and Cross Bay Bridge This project upgrades or replaces sign gantries at the Marine Parkway Bridge and Cross Bay Bridge to improve safety and reliability for motorists. Bridges And Tunnels | Upcoming Procurement | – | – |
| DB Services for Metro-North Railroad Hudson Line Bundle This project will electrify two non-powered segments of the Hudson Line south of Croton Harmon to provide added reliability and flexibility to ensure that emergency or other track outages do… Metro-North Railroad | Upcoming Procurement | – | – |
| West Side Yard Mitigation Construction As part of the MTA’s resilience program, we’re protecting the LIRR West Side Yard from future storm surges by installing a new emergency storm-water pumping system and protective barrier, reducing… Long Island Rail Road | Upcoming Procurement | – | – |
| Atlantic Terminal Water Remediation & Structural Repairs This project investigates and addresses water leaks and water damage within areas of the Atlantic Av-Barclays Center complex to improve station condition and reduce ongoing deterioration. New York City Transit, Long Island Rail Road | Upcoming Procurement | – | – |
| Design-Build Services for Track Intrusion Detection Systems (TIDS) at Two Stations This project will demonstrate the feasibility, performance, and reliability of an artificial intelligence–supported approach to right-of-way intrusion detection and awareness. New York City Transit | Active Procurement | – | – |
Planning (20)
| Project | Stage | Cost | Finish |
|---|---|---|---|
| Brewster Yard Improvements Program We are expanding railcar servicing and maintenance capabilities on Metro-North’s Harlem Line through a planned multi-phase project at the Brewster Complex in Putnam County. The project will include reconfiguring and… Metro-North Railroad | Planned | – | – |
| 25-29 NYCT Signal Modernization Program Modern subway signaling technology has dramatically improved service performance on the L, the 7, and segments of the E/F/M/R where it has been installed. With this Capital Plan, the MTA… New York City Transit | Planned | – | – |
| 25-29 NYCT ADA Improvements (incl. SIR) The MTA is committed to improving transit access for everyone, including customers with disabilities, people traveling with children in strollers, seniors, and more. The 2025-2029 Capital Plan continues the MTA's… New York City Transit | Planned | – | – |
| 25-29 NYCT Station Elevator & Escalator Replacements The MTA is committed to improving transit access for everyone, including customers with disabilities, people traveling with children in strollers, seniors, and more. The 2025-2029 Capital Plan will replace at… New York City Transit | Planned | – | – |
| 25-29 NYCT Station Renewals The MTA is committed to ensuring customers feel comfortable and safe throughout our stations. In the 2025-2029 Capital Plan, the MTA will repair infrastructure elements, add new safety features, improve… New York City Transit | Planned | – | – |
| 25-29 NYCT Line Structure Paint/Repair Line structures provide a safe right-of-way for subway trains above and below ground. NYCT’s network of 251 miles of line structures, have not received adequate investment in past Capital Plans… New York City Transit | Planned | – | – |
| 25-29 NYCT Substation Renewals MTA substations convert high-voltage AC power from utility providers into 650-volt DC power that moves trains. The infrastructure required to support this extensive transit network is vast, complex and often… New York City Transit | Planned | – | – |
| 25-29 NYCT Pump Rooms Pump rooms remove excess water from the subway system on a daily basis and are especially critical to preventing major service disruptions during heavy rainfall. The 2025-2029 Capital Plan will… New York City Transit | Planned | – | – |
| 25-29 LIRR Station Projects The MTA is committed to ensuring customers feel comfortable and safe as they wait for their train. The 2025-2029 Capital Plan will keep stations open, safe, and accessible by replacing… Long Island Rail Road | Planned | – | – |
| 25-29 LIRR Bridge Projects The 2025-2029 Capital Plan will keep service safe and reliable by increasing the annual pace of structural rehabilitation of bridges and ensure longevity of structures by waterproofing bridge decks and… Long Island Rail Road | Planned | – | – |
| 25-29 LIRR Communications and Signal Projects The 2025-2029 Capital Plan will upgrade approximately 12 miles of signals on the Port Jefferson Branch and approximately 17 miles of signals on the Montauk Branch where over half of… Long Island Rail Road | Planned | – | – |
| 25-29 LIRR Power Projects Long Island Rail Road power network is a service-critical asset that powers train service. The 2025-2029 Capital Plan will keep service safe and reliable by renewing substation components or fully… Long Island Rail Road | Planned | – | – |
| 25-29 LIRR Track Projects Long Island Rail Road's track network consists of more than 1,000 miles of rail and 738 switches, 400 crossings, and various other equipment. The 2025-2029 Capital Plan will replace 80… Long Island Rail Road | Planned | – | – |
| 25-29 MNR ADA The MTA is committed to improving transit access for everyone, including customers with disabilities, people traveling with children in strollers, seniors, and more. With the 2025-2029 Capital Plan, Metro-North will… Metro-North Railroad | Planned | – | – |
| 25-29 MNR Station Rehabs The MTA is committed to ensuring customers feel comfortable and safe as they wait for their train. The 2025-2029 Capital Plan will keep stations safe and accessible by replacing and… Metro-North Railroad | Planned | – | – |
| 25-29 MNR Bridge Projects Metro-North has substantial outstanding track investment needs and we must accelerate the pace of our track replacement schedule. The 2025-2029 Capital Plan will keep service safe and reliable and enhance… Metro-North Railroad | Planned | – | – |
| 25-29 MNR Signals Communications and signals assets play an essential role in Metro-North’s safety and on-time performance goals. The 2025-2029 Capital Plan will improve reliability and security by continuing to replace signals, security,… Metro-North Railroad | Planned | – | – |
| 25-29 MNR Substation Projects Metro-North's power network is a service-critical asset that powers train service and is in dire need of investment. The 2025-2029 Capital Plan will improve service reliability by adding new permanent… Metro-North Railroad | Planned | – | – |
| 25-29 MNR Resilience Projects Flooding related to extreme weather events greatly threaten Metro-North operations. The 2025-2029 Capital Plan will implement resilience measures that will protect Metro-North lines against increasingly frequent extreme weather events, including… Metro-North Railroad | Planned | – | – |
| Interborough Express The Interborough Express is a transformative rapid transit project that will connect currently underserved areas of Brooklyn and Queens. It will substantially cut down on travel times between the two… MTA Capital Construction Company | Planned | – | – |
Complete (5)
| Project | Stage | Cost | Finish |
|---|---|---|---|
| NYCT ADA: Package 2 We made six stations newly accessible—Westchester Sq–E Tremont Av, 181 St, Queensboro Plaza, 8 Av, Court Sq, and Woodhaven Blvd—and replaced elevators at Marcy Av and Flushing Av. The package… New York City Transit | Complete | $455 million | Dec 2024 goal was Jan 2024 |
| NYCT ADA: Package 1 As part of the MTA’s commitment to systemwide accessibility, we delivered 17 new elevators across eight stations—7 Av (Brooklyn), Grand St (L), Metropolitan Av (G), Lorimer St (L), E 149… Staten Island Railway, New York City Transit | Complete | $325 million | Apr 2024 goal was Aug 2023 |
| LIRR ADA Station Improvements: Package 1 As part of the MTA’s commitment to systemwide accessibility, we are making improvements at 9 LIRR stations. This project includes making 7 stations newly accessible and replacing elevators and escalators… Long Island Rail Road | Complete | $169 million | Dec 2025 goal was Sep 2025 |
| Rehab Admin Facilities: Replace Boilers at 130 Livingston St This project replaces aging boiler equipment at 130 Livingston St to improve heating reliability and energy performance. New York City Transit | Complete | $2,660,730 | Nov 2025 |
| Signal Tower n/o Parkchester / PEL This project removes an obsolete signal tower structure near Parkchester to support safe, maintainable right-of-way conditions. New York City Transit | Complete | $2,521,628 | Dec 2025 |
Questions
How much is the MTA spending on construction?
The 156 projects in the MTA's project tracker add up to about $17.9 billion where a cost is listed. Many projects in planning or procurement don't have a cost yet.
When will the Second Avenue Subway Phase 2 open?
The tracker lists 1 Phase 2 contract. The biggest, "SAS Ph2: Heavy Civil TBM 116 St / 125 St Stns: Contract 2", is due to finish in Sep 2029. Phase 2 extends the Q train from 96 St up to 125 St in East Harlem, with new stations at 106 St, 116 St and 125 St.
What is the Interborough Express (IBX)?
A planned light rail line along an existing freight track from Bay Ridge, Brooklyn, to Jackson Heights, Queens, about 14 miles. It would connect with up to 17 subway lines and the LIRR. It is in the planning stage in the MTA's tracker.
How many MTA projects are behind schedule?
17 projects have an estimated finish date later than their goal date, and 9 are expected to cost more than their goal budget.
More NYC transit data
- NYC subway ridership: Busiest stations, find your station and an animated subway map, updated daily.
- Every subway station ranked: riders a day, busiest hours, accessibility and elevator reliability for all 424 stations.
- NYC congestion pricing: Zone map, hours, cost and daily data on whether it's working.
- Every subway line ranked: Which line is the worst? On-time rates, delays and a report card for each line.
- NYC bus routes ranked: The busiest, slowest and least reliable buses, with a report card for each route.
- NYC subway crime: Major felonies by year, time of day and station, updated monthly.
- LIRR on-time performance: On-time rates, late and cancelled trains by branch and cause, and ridership.
- Metro-North on-time performance: On-time rates, late and cancelled trains by line and cause, and ridership.
- MTA salaries and overtime: What MTA workers make, the best-paid jobs and overtime, without names.
- NYC bridge and tunnel traffic: Crossings a day on each MTA bridge and tunnel, busiest hours and tolls paid.
- Access-A-Ride report card: Trips, on-time pickups, ride times, no-shows, complaints and phone wait times.
- MTA jobs and what they pay: How many people work at the MTA, typical pay for 80 jobs, hiring and overtime.
- Staten Island Railway: On-time rate, ridership, trains a day, breakdowns and stations.
- Where to get an E-ZPass: Map and list of every place in New York that sells E-ZPass tags.
- OMNY fare cap and guide: How tap-to-pay and the weekly fare cap work, and how fast OMNY replaced the MetroCard.
- NYC bridge and tunnel tolls: What a car or motorcycle pays at every MTA bridge and tunnel in 2026.
- Staten Island Ferry: Riders a day, busiest days and how ridership compares with 2019.
- NYC Ferry ridership: Every NYC Ferry route and stop ranked, and the busiest hours.
- PATH train: Fares, stations and routes, and PATH ridership by month.
- Subway service changes and delays: Delays right now and this weekend's planned work on every line.
- LIRR and Metro-North fare calculator: Peak, off-peak, weekly and monthly fares for every station.
- Live NYC subway map: every route and station on one map, with live train positions.
Data: MTA Capital Project Details: Beginning 2015. Updated Nov 3, 2026.
Source code: github.com/MantieReid/mta-data-analysis · Analysis by Mantie Reid II (CC BY 4.0).
This is an independent data analysis project and is not affiliated with, sponsored by, or endorsed by the Metropolitan Transportation Authority (MTA).
Data is sourced from the MTA through the New York State Open Data Portal. Visualizations, calculations, and interpretations are independently produced. Data may be revised, incomplete, or delayed. For official transit information, visit mta.info.