Skip to content
NYC Data / City Support by Mantie Reid II

Housing violations · Bedford-Stuyvesant (West)

281 Quincy Street, Brooklyn

11216 · 25 apartments · 5 stories · City Council district 36

By · Updated · Data from NYC HPD

C
88open immediately hazardous violations · 352 per 100 apartments
B217Hazardous, open
A73Non-hazardous, open
!378Past the fix-by date

On average, NYC buildings have 19.6 open class C violations per 100 apartments. This building has more.

24 open violations are marked "rent impairing" by HPD, which can be grounds for tenants to pay less rent.

Who owns and manages it

Owning companyGATES CLUSTER DEVELOPMENT, LP
Landlord (head officer or owner)Robyn Lucas

As registered with HPD.

Open problems

All open violations in the building, by type.

  1. Peeling paint and plaster
    99
  2. Other repairs
    74
  3. Missing smoke or CO detector
    40
  4. Leaks and water damage
    32
  5. Broken doors or locks
    31
  6. Plumbing, sinks and toilets
    24
  7. Mold
    21
  8. Roaches
    19
  9. Mice or rats
    16
  10. Electrical problems
    12
  11. Missing window guards
    5
  12. Bedbugs
    4
  13. Lead paint
    2

How fast problems get closed

Typical days from the violation notice to the city closing it, for violations issued in the past 3 years. Fewer is better.

C113 days
from 64 closed · NYC typical: 87 days
B160 days
from 10 closed · NYC typical: 115 days

The legal deadline is 24 hours for class C and 30 days for class B. Closing also needs paperwork, so the real fix can be sooner.

Open hazardous violations

Newest first, the latest 60. Tap a violation number for its full details.

  • C
    Broken doors or locksReplace or repair the self-closing doors that is missing or defective building entrance door hinges , 1st storyIssued Oct 26, 2026 · fix by Nov 9, 2026 overdue · Violation #19330479
  • C
    Other repairsReplace with new the missing side lite at the building entrance , 1st storyIssued Oct 26, 2026 · fix by Nov 1, 2026 overdue · Violation #19330480
  • B
    MoldTrace and repair the source and abate the visible mold condition less than 10 sq ft at ceiling in the kitchenIssued Oct 1, 2026 · fix by Nov 5, 2026 overdue · Violation #19268219
  • B
    MoldTrace and repair the source and abate the visible mold condition less than 10 sq ft at ceiling in the bathroomIssued Oct 1, 2026 · fix by Nov 5, 2026 overdue · Violation #19268218
  • B
    Leaks and water damageProperly repair the source and abate the evidence of a water leak at the ceiling and north wall in the bathroomIssued Jun 29, 2026 · fix by Aug 3, 2026 overdue · Violation #19031555
  • B
    Other repairsProperly repair with similar material the broken or defective wood floor in the kitchenIssued Jun 29, 2026 · fix by Aug 3, 2026 overdue · Violation #19031550
  • C
    Other repairsProperly repair or replace the broken or defective spring balance lower window sash at 1st window from west at north wall (fire escape window) in the 1st room…Issued Jun 29, 2026 · fix by Jul 5, 2026 overdue · Violation #19031551
  • B
    Other repairsProperly repair or replace the broken or defective spring balance lower window sash at 1st window from north at east wall in the kitchenIssued Jun 29, 2026 · fix by Aug 3, 2026 overdue · Violation #19031552
  • C
    Other repairsProperly repair or replace the broken or defective metal cover at 1st baseboard radiator from east at south wall in the kitchenIssued Jun 29, 2026 · fix by Jul 5, 2026 overdue · Violation #19031553
  • B
    Other repairsRepair the flushing apparatus and maintain same so as to flush effectively the water closet in the bathroomIssued Jun 29, 2026 · fix by Aug 3, 2026 overdue · rent impairing · Violation #19031556
  • B
    Broken doors or locksProperly repair or replace the broken or defective door knob at 1st closet from north at east wall in the 2nd private hallway from eastIssued Jun 29, 2026 · fix by Aug 3, 2026 overdue · Violation #19031561
  • B
    Broken doors or locksProperly repair or replace the broken or defective door knob at 1st door from south at west wall in the 5th room from northIssued Jun 29, 2026 · fix by Aug 3, 2026 overdue · Violation #19031562
  • B
    Electrical problemsProperly repair or replace the broken or defective electrical light switch at east wall in the foyerIssued Jun 29, 2026 · fix by Aug 3, 2026 overdue · Violation #19031563
  • B
    Peeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color the west wall in the foyerIssued Jun 29, 2026 · fix by Aug 3, 2026 overdue · Violation #19031564
  • B
    Broken doors or locksReplace with new the missing glass pane at side panel vestibule door at south wall at public hall, 1st storyIssued Jun 29, 2026 · fix by Aug 3, 2026 overdue · Violation #19031568
  • B
    Other repairsProperly repair or replace the broken or defective intercom return panel at east wall in the 2nd private hallway from eastIssued Jun 29, 2026 · fix by Aug 3, 2026 overdue · Violation #19031560
  • B
    Electrical problemsProperly repair or replace the broken or defective electrical light switch at west wall in the bathroomIssued Jun 29, 2026 · fix by Aug 3, 2026 overdue · Violation #19031559
  • B
    MoldTrace and repair the source and abate the visible mold condition greater than 10 sq.ft at the ceiling in the bathroomIssued Jun 29, 2026 · fix by Aug 3, 2026 overdue · Violation #19031558
  • B
    Other repairsProperly repair with similar material the broken or defective ceramic tiles at north wall in the bathroomIssued Jun 29, 2026 · fix by Aug 3, 2026 overdue · Violation #19031557
  • B
    Peeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color the ceiling and north wall in the bathroomIssued Jun 29, 2026 · fix by Aug 3, 2026 overdue · Violation #19031554
  • C
    RoachesAbate the infestation consisting of roaches in the entire apartmentIssued Jun 3, 2026 · fix by Jun 29, 2026 overdue · Violation #18974762
  • C
    Mice or ratsAbate the nuisance consisting of evidence of rats and all underlying causes creating the pest infestations, by using integrated pest management (ipm),…Issued Jun 3, 2026 · fix by Jun 29, 2026 overdue · rent impairing · Violation #18974761
  • B
    Other repairsProperly repair with similar material the broken or defective vinyl floor tiles in the kitchenIssued Feb 26, 2026 · fix by Apr 2, 2026 overdue · Violation #18663289
  • B
    Other repairsProperly repair with similar material the broken or defective ceramic tiles at east wall in the bathroomIssued Feb 25, 2026 · fix by Apr 1, 2026 overdue · Violation #18663333
  • B
    MoldTrace and repair the source and abate the visible mold condition less 10 square feet at west wall in the bathroomIssued Feb 24, 2026 · fix by Mar 31, 2026 overdue · Violation #18671060
  • C
    Leaks and water damageProperly repair the source and abate the evidence of a water leak at ceiling in the bathroomIssued Feb 23, 2026 · fix by Mar 1, 2026 overdue · Violation #18663266
  • B
    Electrical problemsProperly repair or replace the broken or defective electric outlets in the entire apartmentIssued Feb 23, 2026 · fix by Mar 30, 2026 overdue · Violation #18663294
  • B
    Peeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color all walls and ceiling in the bathroomIssued Feb 23, 2026 · fix by Mar 30, 2026 overdue · Violation #18663298
  • B
    Leaks and water damageRepair the leaky and/or defective faucets at sink in the kitchenIssued Feb 23, 2026 · fix by Mar 30, 2026 overdue · Violation #18663320
  • B
    MoldTrace and repair the source and abate the visible mold condition greater than 10 sq ft at north wall inside closet in the 1st room from northIssued Feb 23, 2026 · fix by Mar 30, 2026 overdue · Violation #18663283
  • B
    Electrical problemsProvide a safe and adequate supply of electric service to the fixtures at ceiling in the kitchenIssued Feb 23, 2026 · fix by Mar 30, 2026 overdue · Violation #18663326
  • C
    Peeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color at north wall inside closet in the 1st room from northIssued Feb 23, 2026 · fix by Mar 1, 2026 overdue · Violation #18663286
  • C
    Plumbing, sinks and toiletsRepair the broken or defective connection at wastepipe at wash basin in the bathroomIssued Jan 14, 2026 · fix by Jan 20, 2026 overdue · Violation #18576696
  • B
    Peeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color all walls in the bathroomIssued Jan 14, 2026 · fix by Feb 18, 2026 overdue · Violation #18576701
  • C
    Peeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color the ceiling in the bathroomIssued Jan 14, 2026 · fix by Jan 20, 2026 overdue · Violation #18576700
  • B
    Leaks and water damageProperly repair the source and abate the evidence of a water leak at ceiling in the bathroomIssued Jan 14, 2026 · fix by Feb 18, 2026 overdue · Violation #18576698
  • C
    Plumbing, sinks and toiletsRepair the broken or defective connection at wastepipe at sink in the kitchenIssued Jan 14, 2026 · fix by Jan 20, 2026 overdue · Violation #18576705
  • B
    MoldTrace and repair the source and abate the visible mold condition at ceiling equal to 20 sq. feet in the bathroomIssued Jan 14, 2026 · fix by Feb 18, 2026 overdue · Violation #18576703
  • B
    Leaks and water damageProperly repair the source and abate the evidence of a water leak at west wall in the bathroomIssued Dec 30, 2025 · fix by Feb 3, 2026 overdue · Violation #18534890
  • B
    Broken doors or locksProperly repair or replace the broken or defective inoperative bell-buzzer from building entrance door to return panelIssued Dec 30, 2025 · fix by Feb 3, 2026 overdue · Violation #18534891
  • B
    Leaks and water damageProperly repair the source and abate the evidence of a water leak at west and south wall in the 1st room from northIssued Dec 30, 2025 · fix by Feb 3, 2026 overdue · Violation #18534889
  • C
    Other repairs& 309 m/d law abate the nuisance consisting of security gate at window with fire escape stuck at closed position in the 1st room from northIssued Dec 30, 2025 · fix by Jan 5, 2026 overdue · Violation #18534887
  • B
    Electrical problemsProperly repair or replace the broken or defective electric outlet at south wall in the 1st room from northIssued Dec 30, 2025 · fix by Feb 3, 2026 overdue · Violation #18534886
  • B
    Leaks and water damageRepair the roof so that it will not leak over ceiling in the 1st room from northIssued Dec 30, 2025 · fix by Feb 3, 2026 overdue · rent impairing · Violation #18534888
  • C
    Mice or ratsAbate the nuisance consisting of evidence of rats and all underlying causes creating the pest infestations, by using integrated pest management (ipm),…Issued Oct 27, 2025 · fix by Nov 22, 2025 overdue · rent impairing · Violation #18320071
  • B
    Missing smoke or CO detectorB)(1)(b) hmc, § 12-06, § 12-07, § 12-09 rcny repair, replace or provide an approved and operational carbon monoxide detecting device, installed in accordance…Issued Oct 27, 2025 · fix by Dec 1, 2025 overdue · Violation #18320072
  • B
    Other repairsProperly repair or replace the broken or defective spring balance at window lower sash in the bathroomIssued Oct 27, 2025 · fix by Dec 1, 2025 overdue · Violation #18320066
  • B
    Broken doors or locksProperly repair or replace the broken or defective wood door at entrance in the bathroomIssued Oct 27, 2025 · fix by Dec 1, 2025 overdue · Violation #18320067
  • B
    Missing smoke or CO detectorB)(1)(a) hmc, § 12-01, § 12-03 rcny repair, replace or provide an approved and operational smoke detecting device, installed in accordance with department of…Issued Oct 27, 2025 · fix by Dec 1, 2025 overdue · Violation #18320073
  • B
    Peeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color the north and east wall in the 2nd room from northIssued Oct 27, 2025 · fix by Dec 1, 2025 overdue · Violation #18320068
  • C
    RoachesAbate the infestation consisting of roaches in the entire apartmentIssued Oct 27, 2025 · fix by Nov 22, 2025 overdue · Violation #18320064
  • B
    Plumbing, sinks and toiletsProperly repair or replace the broken or defective floor cabinet at sink in the kitchenIssued Oct 27, 2025 · fix by Dec 1, 2025 overdue · Violation #18320062
  • B
    Peeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color the south wall in the kitchenIssued Oct 27, 2025 · fix by Dec 1, 2025 overdue · Violation #18320070
  • B
    Leaks and water damageRepair the leaky and/or defective faucets faucet at bathtub in the bathroomIssued Oct 27, 2025 · fix by Dec 1, 2025 overdue · Violation #18320063
  • B
    BedbugsAbate the infestation consisting of bedbugs in the entire apartmentIssued Oct 27, 2025 · fix by Dec 1, 2025 overdue · Violation #18320065
  • B
    Peeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color the east and west wall in the foyerIssued Oct 27, 2025 · fix by Dec 1, 2025 overdue · Violation #18320074
  • B
    Broken doors or locksProperly repair or replace the broken or defective intercom door bell and return buzzer from building front entrance door to south wall in the 2nd room from…Issued Oct 27, 2025 · fix by Dec 1, 2025 overdue · Violation #18320069
  • B
    Leaks and water damageProperly repair the source and abate the evidence of a water leak over cieling in the bathroomIssued Oct 8, 2025 · fix by Nov 12, 2025 overdue · Violation #18278093
  • B
    Peeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color the west wall in the 4th room from northIssued Oct 8, 2025 · fix by Nov 12, 2025 overdue · Violation #18278119
  • B
    Plumbing, sinks and toiletsProperly repair with similar material the broken or defective caulking around the sink in the kitchenIssued Oct 8, 2025 · fix by Nov 12, 2025 overdue · Violation #18278125

See every open violation on HPD Online, the city's official site. Violation numbers match.

New violations each year

172017
702018
552019
682020
1232021
792022
882023
1582024
1362025
582026
Everything here comes from HPD's published records. A violation stays open until the landlord certifies the repair and HPD accepts it. Apartment numbers are left out on purpose. 979 violations on record for this building.

Source: NYC Department of Housing Preservation and Development (HPD), Housing Maintenance Code Violations (NYC Open Data wvxf-dwi5) and Buildings Subject to HPD Jurisdiction (kj4p-ruqc), refreshed nightly. Updated November 15, 2026. Apartment numbers are left out on purpose.