On average, NYC buildings have 19.6 open class C violations per 100 apartments. This building has more.
4 open violations are marked "rent impairing" by HPD, which can be grounds for tenants to pay less rent.
Who owns and manages it
As registered with HPD.
Open problems
All open violations in the building, by type.
- Peeling paint and plaster93
- Lead paint52
- Other repairs33
- Mice or rats32
- Leaks and water damage30
- Roaches30
- Mold21
- Broken doors or locks14
- Plumbing, sinks and toilets11
- Electrical problems5
- Missing smoke or CO detector5
- Missing window guards1
How fast problems get closed
Typical days from the violation notice to the city closing it, for violations issued in the past 3 years. Fewer is better.
from 27 closed · NYC typical: 87 days
from 4 closed · NYC typical: 115 days
The legal deadline is 24 hours for class C and 30 days for class B. Closing also needs paperwork, so the real fix can be sooner.
Open hazardous violations
Newest first, the latest 60. Tap a violation number for its full details.
- COther repairsProperly repair or replace the broken or defective lower window sash balance at west wall in the 1st room from north at eastIssued Nov 16, 2026 · Violation #19377739
- CPeeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color at ceiling in the 1st room from north at eastIssued Nov 16, 2026 · Violation #19377732
- CElectrical problemsProvide a safe and adequate supply of electric service to the fixtures outlet at north wall in the 4th room from north at eastIssued Nov 16, 2026 · Violation #19377725
- BMoldTrace and repair the source and abate the visible mold condition greater than 20 sq ft at east wall in the bathroomIssued Nov 16, 2026 · Violation #19377720
- BPeeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color at west wall in the 2nd room from north at eastIssued Nov 16, 2026 · Violation #19377698
- CPeeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color at ceiling in the kitchenIssued Nov 16, 2026 · Violation #19377710
- BPeeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color at east wall in the bathroomIssued Nov 16, 2026 · Violation #19377719
- CLeaks and water damageProperly repair the source and abate the evidence of a water leak at ceiling in the bathroomIssued Nov 2, 2026 · fix by Nov 8, 2026 overdue · Violation #19343931
- CRoachesAbate the infestation consisting of roaches in the entire apartmentIssued Nov 2, 2026 · fix by Nov 28, 2026 · Violation #19343852
- COther repairsProperly repair or replace the broken or defective spring balance at lower sash window at fire escape window in the 4th room from northIssued Nov 2, 2026 · fix by Nov 8, 2026 overdue · Violation #19343926
- BOther repairsProperly repair or replace the broken or defective bell/buzzer intercom system in the kitchenIssued Nov 2, 2026 · fix by Dec 7, 2026 · Violation #19343918
- COther repairsProperly repair with similar material the broken or defective glass at lower window sash at 2nd window from north at east in the 3rd room from eastIssued Nov 2, 2026 · fix by Nov 8, 2026 overdue · Violation #19343871
- CElectrical problemsProvide a safe and adequate supply of electric service to the fixtures at ceiling in the bathroomIssued Nov 2, 2026 · fix by Nov 8, 2026 overdue · Violation #19343899
- BPeeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color at ceiling in the kitchenIssued Nov 2, 2026 · fix by Dec 7, 2026 · Violation #19343908
- BPeeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color at ceiling in the bathroomIssued Nov 2, 2026 · fix by Dec 7, 2026 · Violation #19343914
- CRoachesAbate the infestation consisting of roaches in the entire apartmentIssued Nov 2, 2026 · fix by Nov 28, 2026 · Violation #19343903
- BOther repairsProperly repair with similar material the broken or defective wood baseboard at east wall in the bathroomIssued Nov 2, 2026 · fix by Dec 7, 2026 · Violation #19344059
- CLeaks and water damageProperly repair the source and abate the evidence of a water leak at ceiling in the closet in the 4th room from eastIssued Nov 2, 2026 · fix by Nov 8, 2026 overdue · Violation #19344058
- CMice or ratsAbate the infestation consisting of mice in the entire apartmentIssued Nov 2, 2026 · fix by Nov 28, 2026 · Violation #19344055
- CRoachesAbate the infestation consisting of roaches in the entire apartmentIssued Nov 2, 2026 · fix by Nov 28, 2026 · Violation #19344054
- BMoldTrace and repair the source and abate the visible mold condition at ceiling and north wall, greater than 10 sq feet in the bathroomIssued Nov 2, 2026 · fix by Dec 7, 2026 · Violation #19343877
- CLeaks and water damageRepair the leaky and/or defective faucets at shower body at bathtub in the bathroomIssued Nov 2, 2026 · fix by Nov 8, 2026 overdue · Violation #19343896
- CMice or ratsAbate the infestation consisting of mice in the entire apartmentIssued Nov 2, 2026 · fix by Nov 28, 2026 · Violation #19343916
- CLeaks and water damageRepair the leaky and/or defective faucets at kitchen sink in the kitchenIssued Nov 2, 2026 · fix by Nov 8, 2026 overdue · Violation #19343937
- BPeeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color at south wall in the 4th room from northIssued Nov 2, 2026 · fix by Dec 7, 2026 · Violation #19343933
- CMice or ratsAbate the infestation consisting of mice in the entire apartmentIssued Oct 13, 2026 · fix by Nov 8, 2026 overdue · Violation #19291409
- CLead paint- correct the lead-based paint hazard - paint that tested positive for lead content and that is peeling or on a deteriorated subsurface - using work practices…Issued Oct 13, 2026 · fix by Nov 6, 2026 overdue · Violation #19296330
- CLead paint- correct the lead-based paint hazard - paint that tested positive for lead content and that is peeling or on a deteriorated subsurface - using work practices…Issued Oct 13, 2026 · fix by Nov 6, 2026 overdue · Violation #19296329
- CLead paint- correct the lead-based paint hazard - paint that tested positive for lead content and that is peeling or on a deteriorated subsurface - using work practices…Issued Oct 13, 2026 · fix by Nov 6, 2026 overdue · Violation #19296331
- CLead paint- correct the lead-based paint hazard-paint that is peeling or on a deteriorated subsurface and either tested inconclusive for lead content at 0.5mg/cm2 or…Issued Oct 13, 2026 · fix by Nov 6, 2026 overdue · Violation #19296336
- CLead paint- correct the lead-based paint hazard - paint that tested positive for lead content and that is peeling or on a deteriorated subsurface - using work practices…Issued Oct 13, 2026 · fix by Nov 6, 2026 overdue · Violation #19296335
- CLead paint- correct the lead-based paint hazard-paint that is peeling or on a deteriorated subsurface and either tested inconclusive for lead content at 0.5mg/cm2 or…Issued Oct 13, 2026 · fix by Nov 6, 2026 overdue · Violation #19296334
- CLead paint- correct the lead-based paint hazard-paint that is peeling or on a deteriorated subsurface and either tested inconclusive for lead content at 0.5mg/cm2 or…Issued Oct 13, 2026 · fix by Nov 6, 2026 overdue · Violation #19296333
- CLead paint- correct the lead-based paint hazard - paint that tested positive for lead content and that is peeling or on a deteriorated subsurface - using work practices…Issued Oct 13, 2026 · fix by Nov 6, 2026 overdue · Violation #19296332
- BPeeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color at north wall in the 4th room from east at northIssued Oct 13, 2026 · fix by Nov 17, 2026 · Violation #19291403
- BPeeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color at ceiling in the foyerIssued Oct 13, 2026 · fix by Nov 17, 2026 · Violation #19291405
- BPeeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color at south wall in the kitchenIssued Oct 13, 2026 · fix by Nov 17, 2026 · Violation #19291408
- BOther repairsProperly repair with similar material the broken or defective vinyl floor tiles in the 4th room from northIssued Aug 14, 2026 · fix by Sep 18, 2026 overdue · Violation #19142047
- BOther repairsProperly repair or replace the broken or defective intercom system at public hall, 1st storyIssued Aug 14, 2026 · fix by Sep 18, 2026 overdue · Violation #19142096
- CLeaks and water damageProperly repair the source and abate the evidence of a water leak at the ceiling in the bathroomIssued Aug 14, 2026 · fix by Aug 20, 2026 overdue · Violation #19141985
- BPeeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color the east wall in the bathroomIssued Aug 14, 2026 · fix by Sep 18, 2026 overdue · Violation #19142022
- BPeeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color the ceiling in the bathroomIssued Aug 14, 2026 · fix by Sep 18, 2026 overdue · Violation #19142004
- BPeeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color the ceiling in the 4th room from north at westIssued Aug 14, 2026 · fix by Sep 18, 2026 overdue · Violation #19142078
- BOther repairsProperly repair with similar material the broken or defective vinyl floor tiles in the kitchenIssued Aug 14, 2026 · fix by Sep 18, 2026 overdue · Violation #19141970
- BPeeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color the ceiling in the bathroomIssued Aug 14, 2026 · fix by Sep 18, 2026 overdue · Violation #19141973
- COther repairsProperly repair with similar material the broken or defective ceramic wall tiles in the bathroomIssued Aug 14, 2026 · fix by Aug 20, 2026 overdue · Violation #19141982
- BPlumbing, sinks and toiletsProperly secure the loose wash basin in the bathroomIssued Aug 14, 2026 · fix by Sep 18, 2026 overdue · Violation #19141994
- BOther repairsProperly repair with similar material the broken or defective vinyl floor tiles in the 3rd room from northIssued Aug 14, 2026 · fix by Sep 18, 2026 overdue · Violation #19142012
- BPlumbing, sinks and toiletsProperly repair with similar material the broken or defective caulking around the bathtub in the bathroomIssued Aug 14, 2026 · fix by Sep 18, 2026 overdue · Violation #19142020
- BPeeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color the ceiling in the kitchenIssued Aug 14, 2026 · fix by Sep 18, 2026 overdue · Violation #19142023
- CElectrical problemsProvide a safe and adequate supply of electric service to the fixtures electrical outlet at the west wall in the 3rd room from northIssued Aug 14, 2026 · fix by Aug 20, 2026 overdue · Violation #19142027
- CMice or ratsAbate the infestation consisting of mice in the entire apartmentIssued Aug 14, 2026 · fix by Sep 9, 2026 overdue · Violation #19142028
- BPeeling paint and plasterRepair the broken or defective plastered surfaces and paint in a uniform color the ceiling in the 4th room from northIssued Aug 14, 2026 · fix by Sep 18, 2026 overdue · Violation #19142051
- CRoachesAbate the infestation consisting of roaches in the entire apartmentIssued Aug 14, 2026 · fix by Sep 9, 2026 overdue · Violation #19142069
- CMice or ratsAbate the infestation consisting of mice in the entire apartmentIssued Aug 14, 2026 · fix by Sep 9, 2026 overdue · Violation #19142076
- BLeaks and water damageProperly repair the source and abate the evidence of a water leak at the ceiling in the 4th room from north at westIssued Aug 14, 2026 · fix by Sep 18, 2026 overdue · Violation #19142077
- BOther repairsProperly repair or replace the broken or defective mailbox at public hall, 1st storyIssued Aug 14, 2026 · fix by Sep 18, 2026 overdue · Violation #19142097
- BPeeling paint and plasterProperly repair with similar material the broken or defective plaster with fire rated material at the north and south walls at public hall, 2nd storyIssued Aug 14, 2026 · fix by Sep 18, 2026 overdue · Violation #19142098
- BOther repairsProperly repair with similar material the broken or defective ceramic floor tiles in the bathroomIssued Aug 14, 2026 · fix by Sep 18, 2026 overdue · Violation #19142758
- BOther repairsProperly repair with similar material the broken or defective vinyl floor tiles in the 2nd room from eastIssued Aug 14, 2026 · fix by Sep 18, 2026 overdue · Violation #19142760
See every open violation on HPD Online, the city's official site. Violation numbers match.
New violations each year
Source: NYC Department of Housing Preservation and Development (HPD), Housing Maintenance Code Violations (NYC Open Data wvxf-dwi5) and Buildings Subject to HPD Jurisdiction (kj4p-ruqc), refreshed nightly. Updated November 15, 2026. Apartment numbers are left out on purpose.